top of page
APPLICATION  FOR  NEW  CONNECTION

Requirements

For Permanent House Connection:

•  Electrical Plan

•  Electrical Permit

•  Certificate of Final Inspection & Completion

•  Certificate of Occupancy

•  Payment of P300 service fee

•  Payment of 1 month Bill deposit (based on the

    electrical plan)

•  Signing of Contract (P50.00 Notarial Fee)

Temporary Connection for Bunk Houses:

•  Electrical Plan

•  Permit for temporary house connection

electrical-plan-house.jpg

Process Flow

⚈  Attend Pre-Membership Education Seminar (PMES) for those who are not yet a member

     Schedule for PMES:

      Tuesday, 8:00AM - 12:00NN  (via ZOOM)

       Friday,    8:00AM - 12:00NN  (At Main Office) 

   

⚈  Secure all  requirements and documents from your Local Government Unit

    • Provide drawing of location of map

     • Electrical Lay-out Plan signed by PEE.

     • Electrical Permit

     • Certificate of final electrical inspection (Signed by the Municipal Engineer/BFP/PEE --- Original Copy)

     • Photocopy of valid ID (any government issued ID)

       

⚈  Submit requirements to Institutional Service Department(ISD) office for evaluation

    • Refer to an Electrical practitioner or to your nearest Barangay Electrician. 

     • Please install the service entrance based on your electrical plan. So that when the inspector comes, it is already prepared.

    

⚈  ISD will schedule for the Service Entrance inspection

    • The  inspector will check the specifications and sizes used based on your submitted electrical plan.

⚈  If approved, proceed to ISD office for payment and signing of contract.

     • Service fee of P300

      • Notarial fee of P50

      • 1 month bill deposit based on the load of your electrical plan

      * If not approved, comply all necessary improvements. ISD will schedule house wiring inspection again.

⚈  Issuance of Connection Order

⚈  Forward Connection Order to Technical Service Department(TSD) office for execution of servicing